textarchive.ru

Главная > Документ


PORT MANAGEMENT OFFICE – SOUTH HARBOR

Port District Office - Manila Bldg., 22 MDSF St., South Harbor, Port Area, Manila

Telephone No. (02) 525-5264: Facsimile No.: (02) 527-66-71

BIDDING DOCUMENTS

(Procurement of Infrastructure Projects)

Contract No./ Title:

PMOSH-RM0512-A120056

Repair of rock bulkhead & repair/repainting of Ferry Landing Terminal at Slip 14, South Harbor, Port Area, Manila.

PHILIPPINE PORTS AUTHORITY

PMO-South Harbor

Engineering Services Division

South Harbor, Port Area, Manila

Telefax # (02) 527-66-71

Tel # (02) 525 5264 loc. 522 / 523 / 524

TABLE OF CONTENTS

PMO-South Harbor 1

Section I. 3

Invitation to Bid 3

Section II. 6

Instructions to Bidders 6

Section III. 32

Bid Data Sheet 32



Section I.

Invitation to Bid

PORT MANAGEMENT OFFICE – SOUTH HARBOR

PDO Manila/Northern Luzon Bldg., 22 MDSF St., South Harbor, Port Area, Manila

Telephone No.: (02) 525-5264 : Facsimile No.: 527-6671

INVITATION TO BID

FOR THE:

Repair of rock bulkhead & repair/repainting of Ferry Landing Terminal at Slip 14, South Harbor, Port Area, Manila

The Philippine Ports Authority – PORT MANAGEMENT OFFICE – SOUTH HARBOR, through the Corporate Budget of the Authority for CY 2011, intends to apply the sum of P 3,277,520.00being the Approved Budget for the Contract (ABC) to payments under the contract for the Repair of rock bulkhead & repair/repainting of Ferry Landing Terminal, Slip 14, South Harbor, Port Area, Manila(PMOSH-RM0512 – A120056).Bids received in excess of the ABC shall be automatically rejected at bid opening.

The Philippine Ports Authority now invites bids for the following Scope of Works: 1. Demolition/Excavation and disposal of debris; 2. Steel works; 3. Carpentry works; 4. Supply and installation of Panaflex Billboard; 5. Electrical works; 6. Tinsmithry; 7. Tile and Plumbing works; 8. Supply & installation of doors and windows; 9. Painting works; 10. Fendering system; 11. Rock works and fill; 11. Rebar works; 12. Concreting works Completion of the Works is required in ONE HUNDRED TWENTY TWO (122) CALENDAR DAYS.Bidders should have completed, within ten (10) years from the date of submission and receipt of bids, a contract similar to the Project. The description of an eligible bidder is contained in the Bidding Documents, particularly, in Section II. Instructions to Bidders.

The Minimum Equipment Requirement, Owned, Leased and/or Under Purchase Agreement, for this project are: 1-Unit Air compressor w/ breaker (186 CFM); 1-Unit Isuzu elf (2 tons capacity); 1-Unit Air compressor w/ 1 breaker (125 CFM); 1-Unit Tile cutter; 1-Unit Electric Grinder; 1-Unit Oxy-acetylene cutting outfit; 1-Unit bar cutter (electric); 1-Unit Concrete mixer (one bagger); 1-Unit Concrete vibrator (3.5hp); 1-Unit A-frame w/ one tonner chain block; 1-Unit Heavy duty A-frame w/ two tonner chain block; 1-Unit Bar bender (electric).

Bidding will be conducted through open competitive bidding procedures using non-discretionary pass/fail criterion as specified in the Revised Implementing Rules and Regulations (IRR) of Republic Act 9184 (R.A. 9184), otherwise known as the "Government Procurement Reform Act."

Bidding is restricted to Filipino citizens/sole proprietorships, partnerships or organizations with at least seventy five percent (75%) interest or outstanding capital stock belonging to citizens of the Philippines.

Interested bidders may obtain further information from the Bids and Awards Committee and inspect the Bidding Documents at the address given below from 8:00 a. m. to 5:00 p.m.

A complete set of Bidding Documents may be purchased by interested Bidders or its authorized representative (with authorization letter) from the address below and upon payment of a non-refundable fee for the Bidding Documents in the amount of FIVE THOUSAND PESOS (P 5,000.00).

It may also be downloaded from the website of the Philippine Government Electronic Procurement System (PhiIGEPS) and the website of the Procuring Entity, provided that bidders shall pay the fee for the Bidding Documents not later than the submission of their bids.

The Bids and Awards Committee will hold a Pre-Bid Conference on 09 August 2012 at 10:00 A.M.at the ESD-Conference Room, Mezanine, PDO-Mla. Bldg., Muelle De San Francisco (MDSF) St., South Harbor, Port Area, Manila, which shall be open to all interested parties who have purchased the Bidding Documents.

Bids must be delivered to the address below on or before 9:00 a.m. of 23 August 2012at the Bids and Awards Committee (BAC) Office, Engineering Services Division (ESD), Mezanine, PDO-Mla. Bldg., M.D.S.F. St., South Harbor, Port Area, Manila. All bids must be accompanied by a Bid Security in accordance with Section 27.2 of the Revised IRR of R.A. 9184. Bids will be opened in the presence of the bidder or its authorized representatives who choose to attend at the address below on 23 August 2012at 10:00 a.m. Late bids shall not be accepted.

• Required PCAB Registration : Small B“Port, Harbor & Offshore Engineering.”

The Philippine Ports Authority reserves the right to accept or reject any bid, to annul the bidding process, and to reject all bids at any time prior to contract award, without thereby incurring any liability to the affected bidder or bidders.

For further information, please refer to:

BAC Secretariat, Mezanine, Engineering Services Division, PMO South Harbor, PDO-Mla. Bldg., South Harbor, Port Area, Manila. Tel. Nos. (02) 525-5264 loc.522/523/524;Website:.ph

ANDRES C. CANDAROMA, JR.

BAC Chairman











Section II.

Instructions to Bidders

TABLE OF CONTENTS

A.General 9

.1.3.Source of Funds 9

.1.4.Corrupt, Fraudulent, Collusive, and Coercive Practices 9

.1.8.Conflict of Interest 10

.1.11.Eligible Bidders 11

.1.17.Bidder’s Responsibilities 13

.1.26.Origin of GOODS and Services 14

.bcontracts 14

B.Contents of Bidding Documents 15

.1.31.Pre-Bid Conference 15

.1.35.Clarification and Amendment of Bidding Documents 15

C.Preparation of Bids 16

.1.39.Language of Bids 16

.1.40.Documents Comprising the Bid: Eligibility and Technical Components 16

.1.42.Documents Comprising the Bid: Financial Component 18

.1.45.Alternative Bids 18

.1.49.Bid Prices 19

.1.54.Bid Currencies 19

.1.58.Bid Validity 20

.1.61.Bid Security 20

.1.67.Format and Signing of Bids 21

.1.73.Sealing and Marking of Bids 22

bmission and Opening of Bids 23

.1.79.Deadline for Submission of Bids 23

.1.80.Late Bids 23

.1.81.Modification and Withdrawal of Bids 23

.1.86.Opening and Preliminary Examination of Bids 24

E.Evaluation and Comparison of Bids 25

.1.94.Process to be Confidential 25

.1.97.Clarification of Bids 25

.1.98.Detailed Evaluation and Comparison of Bids 25

.1.105.Post Qualification 26

.1.112.Reservation Clause 27

F.Award of Contract 28

.1.116.Contract Award 28

.1.120.Signing of the Contract 29

.1.125.Performance Security 30

.1.129.Notice to Proceed 31

A.General

      1. Scope of Bid. The name and identification number of the Contract is provided in the BDS.

      2. The successful bidder will be expected to complete the Works by the intended completion date specified in SCC.

      3. Source of Funds

        The Procuring Entity has a budget or has applied for or received funds from the Funding Source named in the BDS, and in the amount indicated in the BDS. It intends to apply part of the funds received for the Project, as defined in the BDS, to cover eligible payments under the Contract for the Works.

      4. Corrupt, Fraudulent, Collusive, and Coercive Practices

      5. The Procuring Entity, as well as bidders and contractors, shall observe the highest standard of ethics during the procurement and execution of the contract. In pursuance of this policy, the Funding Source:

        1. defines, for purposes of this provision, the terms set forth below as follows:

          1. "corrupt practice" means behavior on the part of officials in the public or private sectors by which they improperly and unlawfully enrich themselves, others, or induce others to do so, by misusing the position in which they are placed, and includes the offering, giving, receiving, or soliciting of anything of value to influence the action of any such official in the procurement process or in contract execution; entering, on behalf of the Procuring Entity, into any contract or transaction manifestly and grossly disadvantageous to the same, whether or not the public officer profited or will profit thereby, and similar acts as provided in Republic Act 3019;

          2. "fraudulent practice" means a misrepresentation of facts in order to influence a procurement process or the execution of a contract to the detriment of the Procuring Entity, and includes collusive practices among Bidders (prior to or after Bid submission) designed to establish bid prices at artificial, non-competitive levels and to deprive the Procuring Entity of the benefits of free and open competition;

          3. “collusive practices” means a scheme or arrangement between two or more bidders, with or without the knowledge of the Procuring Entity, designed to establish bid prices at artificial, non-competitive levels; and

          4. “coercive practices” means harming or threatening to harm, directly or indirectly, persons, or their property to influence their participation in a procurement process, or affect the execution of a contract;

        2. will reject a proposal for award if it determines that the bidder recommended for award has engaged in corrupt or fraudulent practices in competing for the Contract; and

        3. will declare a firm ineligible, either indefinitely or for a stated period of time, to be awarded Contract funded by the Funding Source if it at any time determines that the firm has engaged in corrupt or fraudulent practices in competing or, or in executing, a Contract funded by the Funding Source.

      1. Further, the Procuring Entity will seek to impose the maximum civil, administrative, and/or criminal penalties available under the applicable laws on individuals and organizations deemed to be involved in any of the practices mentioned in ITB Clause 3.1A.

      2. Furthermore, the Funding Source and the Procuring Entity reserve the right to inspect and audit records and accounts of a contractor in the bidding for and performance of a contract themselves or through independent auditors as reflected in the GCC.

      3. Conflict of Interest

      4. All bidders found to have conflicting interests shall be disqualified to participate in the procurement at hand, without prejudice to the imposition of appropriate administrative, civil, and criminal sanctions. A Bidder may be considered to have conflicting interests with another Bidder in any of the events described in paragraphs (a) through (c) and a general conflict of interest in any of the circumstances set out in paragraphs (d) through (g) below:

        1. A Bidder has controlling shareholders in common with another Bidder;

        2. A Bidder receives or has received any direct or indirect subsidy from any other Bidder;

        3. A Bidder has the same legal representative as that of another Bidder for purposes of this Bid;

        4. A Bidder has a relationship, directly or through third parties, that puts them in a position to have access to information about or influence on the bid of another Bidder or influence the decisions of the Procuring Entity regarding this bidding process. This will include a firm or an organization who lends, or temporarily seconds, its personnel to firms or organizations which are engaged in consulting services for the preparation related to procurement for or implementation of the project if the personnel would be involved in any capacity on the same project;

        5. A Bidder submits more than one bid in this bidding process. However, this does not limit the participation of subcontractors in more than one bid;

        6. A Bidder who participated as a consultant in the preparation of the design or technical specifications of the goods and related services that are the subject of the bid; or

        7. A Bidder who lends, or temporary seconds, its personnel to firms or organizations which are engaged in consulting services for the preparation related to procurement for or implementation of the project, if the personnel would be involved in any capacity on the same project.

      5. In accordance with Section 47 of the IRR of RA 9184, all Bidding Documents shall be accompanied by a sworn affidavit of the Bidder that it is not related to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), members of the Technical Working Group (TWG), members of the BAC Secretariat, the head of the Project Management Office (PMO) or the end-user unit, and the project consultants, by consanguinity or affinity up to the third civil degree. On the part of the bidder, this Clause shall apply to the following persons:

        1. If the Bidder is an individual or a sole proprietorship, to the Bidder himself;

        2. If the Bidder is a partnership, to all its officers and members;

        3. If the Bidder is a corporation, to all its officers, directors, and controlling stockholders; and

        4. If the Bidder is a joint venture (JV), the provisions of items (a), (b), or (c) of this Clause shall correspondingly apply to each of the members of the said JV, as may be appropriate.

        Relationship of the nature described above or failure to comply with this Clause will result in the automatic disqualification of a Bidder.

      6. Eligible Bidders

      7. Unless otherwise indicated in the BDS,the following persons shall be eligible to participate in this Bidding:

        1. Duly licensed Filipino citizens/sole proprietorships;

        2. Partnerships duly organized under the laws of the Philippines and of which at least seventy five percent (75%) of the interest belongs to citizens of the Philippines;

        3. Corporations duly organized under the laws of the Philippines, and of which at least seventy five percent (75%) of the outstanding capital stock belongs to citizens of the Philippines;

        4. Cooperatives duly organized under the laws of the Philippines, and of which at least seventy five percent (75%) of the interest belongs to citizens of the Philippines; and

        5. Persons/entities forming themselves into a JV, i.e., a group of two (2) or more persons/entities that intend to be jointly and severally responsible or liable for a particular contract: Provided, however, that, in accordance with Letter of Instructions No. 630, Filipino ownership or interest of the joint venture concerned shall be at least seventy five percent (75%): Provided, further, that joint ventures in which Filipino ownership or interest is less than seventy five percent (75%) may be eligible where the structures to be built require the application of techniques and/or technologies which are not adequately possessed by a person/entity meeting the seventy five percent (75%) Filipino ownership requirement: Provided, finally, that in the latter case, Filipino ownership or interest shall not be less than twenty five percent (25%). For this purpose Filipino ownership or interest shall be based on the contributions of each of the members of the joint venture as specified in their JVA.

      8. The Procuring Entity may also invite foreign bidders when provided for under any Treaty or International or Executive Agreement as specified in the BDS.

      9. Government Corporate Entities may be eligible to participate only if they can establish that they (a) are legally and financially autonomous, (b) operate under commercial law, and (c) are not dependent agencies of the GOP or the Procuring Entity.

      10. Unless otherwise provided in the BDS, the Bidder must have completed at least one contract similar to the Project the value of which, adjusted to current prices using the National Statistics Office consumer price index, must be at least equivalent to a percentage of the ABC stated in the BDS.

For this purpose, contracts similar to the Project shall be those described in the BDS, and completed within the period stated in the Invitation to Bid and ITB Clause C.

      1. Unless otherwise provided in the BDS, the Bidder must submit a computation of its Net Financial Contracting Capacity (NFCC) or a Commitment from a Universal or Commercial bank to extend a credit line in its favor if awarded the contract for this project (CLC).

        The NFCC, computed using the following formula, must be at least equal to the ABC to be bid:

NFCC = [(Current assets minus current liabilities) (K)] minus the value of all outstanding or uncompleted portions of the projects under ongoing contracts, including awarded contracts yet to be started coinciding with the contract for this Project.

Where:

K = 10 for a contract duration of one year or less, 15 for a contract duration of more than one year up to two years, and 20 for a contract duration of more than two years.

The CLC must be at least equal to ten percent (10%) of the ABC for this Project. If issued by a foreign bank, it shall be confirmed or authenticated by a Universal or Commercial Bank. In the case of local government units (LGUs), the Bidder may also submit CLC from other banks certified by the Bangko Sentral ng Pilipinas (BSP) as authorized to issue such financial instrument.

      1. Bidder’s Responsibilities

      2. The Bidder or its duly authorized representative shall submit a sworn statement in the form prescribed in Section IX. Bidding Forms as required in ITB Clause C.

      3. The Bidder is responsible for the following:

        1. Having taken steps to carefully examine all of the Bidding Documents;

        2. Having acknowledged all conditions, local or otherwise, affecting the implementation of the contract;

        3. Having made an estimate of the facilities available and needed for the contract to be bid, if any; and

        4. Having complied with its responsibility to inquire or secure Supplemental/Bid Bulletin/s as provided under ITB Clause B.

        5. Ensuring that it is not “blacklisted” or barred from bidding by the GOP or any of its agencies, offices, corporations, or LGUs, including foreign government/foreign or international financing institution whose blacklisting rules have been recognized by the GPPB;

        6. Ensuring that each of the documents submitted in satisfaction of the bidding requirements is an authentic copy of the original, complete, and all statements and information provided therein are true and correct;

        7. Authorizing the Head of the Procuring Entity or its duly authorized representative/s to verify all the documents submitted;

        8. Ensuring that the signatory is the duly authorized representative of the Bidder, and granted full power and authority to do, execute and perform any and all acts necessary and/or to represent the Bidder in the bidding, with the duly notarized Secretary’s Certificate attesting to such fact, if the Bidder is a corporation, partnership, cooperative, or joint venture;

        9. Complying with the disclosure provision under Section 47 of the Act in relation to other provisions of Republic Act 3019; and

        10. Complying with existing labor laws and standards, if applicable.

Failure to observe any of the above responsibilities shall be at the risk of the Bidder concerned.

      1. The Bidder, by the act of submitting its bid, shall be deemed to have inspected the site and determined the general characteristics of the contract works and the conditions for this Project. Unless otherwise indicated in the BDS, failure to furnish all information or documentation required in this Bidding Documents shall result in the rejection of the bid and the disqualification of the Bidder.

      2. It shall be the sole responsibility of the prospective bidder to determine and to satisfy itself by such means as it considers necessary or desirable as to all matters pertaining to this Project, including: (a) the location and the nature of the contract, project, or work; (b) climatic conditions; (c) transportation facilities; (c) nature and condition of the terrain, geological conditions at the site communication facilities, requirements, location and availability of construction aggregates and other materials, labor, water, electric power and access roads; and (d) other factors that may affect the cost, duration and execution or implementation of the contract, project, or work.

      3. The Procuring Entity shall not assume any responsibility regarding erroneous interpretations or conclusions by the prospective or eligible bidder out of the data furnished by the procuring entity.

      4. Before submitting their bids, the Bidders are deemed to have become familiar with all existing laws, decrees, ordinances, acts and regulations of the Philippines which may affect the contract in any way.

      5. The Bidder shall bear all costs associated with the preparation and submission of his bid, and the Procuring Entity will in no case be responsible or liable for those costs, regardless of the conduct or outcome of the bidding process.

      6. Bidders should note that the Procuring Entity will only accept bids only from those that have paid the nonrefundable fee for the Bidding Documents at the office indicated in the Invitation to Bid.

      7. Origin of GOODS and Services

        Unless otherwise indicated in the BDS, there is no restriction on the origin of Goods, or Contracting of Works or Services other than those prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations.

      8. Subcontracts

      9. Unless otherwise specified in the BDS, the Bidder may subcontract portions of the Works to an extent as may be approved by the Procuring Entity and stated in the BDS. However, subcontracting of any portion shall not relieve the Bidder from any liability or obligation that may arise from the contract for this Project.

      10. Subcontractors must submit the documentary requirements under ITB Clause C and comply with the eligibility criteria specified in the BDS. In the event that any subcontractor is found by the Procuring Entity to be ineligible, the subcontracting of such portion of the Works shall be disallowed.

      11. The Bidder may identify the subcontractor to whom a portion of the Works will be subcontracted at any stage of the bidding process or during contract implementation. If the Bidder opts to disclose the name of the subcontractor during bid submission, the Bidder shall include the required documents as part of the technical component of its bid.

B.Contents of Bidding Documents

      1. Pre-Bid Conference

      2. If so specified in the BDS, a pre-bid conference shall be held at the venue and on the date indicated therein, to clarify and address the Bidders’ questions on the technical and financial components of this Project.

      3. Bidders are encouraged to attend the pre-bid conference to ensure that they fully understand the Procuring Entity’s requirements. Non-attendance of the Bidder will in no way prejudice its bid; however, the Bidder is expected to know the changes and/or amendments to the Bidding Documents discussed during the pre-bid conference.

      4. Any statement made at the pre-bid conference shall not modify the terms of the bidding documents unless such statement is specifically identified in writing as an amendment thereto and issued as a Supplemental/Bid Bulletin.

      5. Clarification and Amendment of Bidding Documents

      6. Bidders who have purchased the Bidding Documents may request for clarification(s) on any part of the Bidding Documents or for an interpretation. Such a request must be in writing and submitted to the Procuring Entity at the address indicated in the BDS at least ten (10) calendar days before the deadline set for the submission and receipt of Bids.

      7. Supplemental/Bid Bulletins may be issued upon the Procuring Entity’s initiative for purposes of clarifying or modifying any provision of the Bidding Documents not later than seven (7) calendar days before the deadline for the submission and receipt of Bids. Any modification to the Bidding Documents shall be identified as an amendment.

      8. Any Supplemental/Bid Bulletin issued by the BAC shall also be posted on the Philippine Government Electronic Procurement System (PhilGEPS) and the website of the Procuring Entity concerned, if available. It shall be the responsibility of all Bidders who secure the Bidding Documents to inquire and secure Supplemental/Bid Bulletins that may be issued by the BAC. However, bidders who have submitted bids before the issuance of the Supplemental/Bid Bulletin must be informed and allowed to modify or withdraw their bids in accordance with ITB Clause D.

C.Preparation of Bids

      1. Language of Bids

        The Bid, as well as all correspondence and documents relating to the Bid exchanged by the Bidder and the Procuring Entity, shall be written in English. Supporting documents and printed literature furnished by the Bidder may be in another language provided they are accompanied by an accurate translation in English certified by the appropriate embassy or consulate in the Philippines, in which case the English translation shall govern, for purposes of interpretation of the Bid.

      2. Documents Comprising the Bid: Eligibility and Technical Components

      3. Unless otherwise indicated in the BDS, the first envelope shall contain the following eligibility and technical documents:

        1. Eligibility Documents –

              Class "A" Documents:

          1. Registration certificate from the Securities and Exchange Commission (SEC), Department of Trade and Industry (DTI) for sole proprietorship, or Cooperative Development Authority (CDA) for cooperatives, or any proof of such registration as stated in the BDS;

          2. Mayor’s permit issued by the city or municipality where the principal place of business of the prospective bidder is located;

          3. Statement of all its ongoing and completed government and private contracts within ten (10) years from the submission of bids, unless otherwise stated in the BDS, including contracts awarded but not yet started, if any. The statement shall include, for each contract, the following:

            1. name of the contract;

            2. date of the contract;

            3. contract duration;

            4. owner’s name and address;

            5. nature of work;

            6. contractor’s role (whether sole contractor, subcontractor, or partner in a JV) and percentage of participation;

            7. total contract value at award;

            8. date of completion or estimated completion time;

            9. total contract value at completion, if applicable;

            10. percentages of planned and actual accomplishments, if applicable;

            11. value of outstanding works, if applicable;

            12. the statement shall be supported by the notices of award and/or notices to proceed issued by the owners; and

            13. the statement shall be supported by the Constructors Performance Evaluation System (CPES) rating sheets, and/or certificates of completion and owner’s acceptance, if applicable;

          4. Unless otherwise provided in the BDS, valid Philippine Contractors Accreditation Board (PCAB) license and registration for the type and cost of the contract for this Project;

          5. Audited financial statements, showing, among others, the prospective total and current assets and liabilities, stamped “received” by the BIR or its duly accredited and authorized institutions, for the preceding calendar year which should not be earlier than two (2) years from the date of bid submission;

          6. NFCC computation or CLC in accordance with ITB Clause A; and

        Class "B" Document:

          1. If applicable, valid Joint Venture Agreement (JVA) or, in lieu thereof, duly notarized statements from all the potential joint venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful shall be included in the bid.

        1. Technical Documents –

          1. Bid security as prescribed in ITB Clause C. If the Bidder opts to submit the bid security in the form of:

            1. a bank draft/guarantee or an irrevocable letter of credit issued by a foreign bank, it shall be accompanied by a confirmation from a Universal or Commercial Bank; or

            2. a surety bond accompanied by a certification coming from an authorized Insurance Commission that a surety or insurance company is authorized to issue such instrument;

          2. Project Requirements, which shall include the following:

            1. Organizational chart for the contract to be bid;

            2. List of contractor’s personnel (viz, project Manager, Project Engineers, Materials Engineers, and Foremen), to be assigned to the contract to be bid, with their complete qualification and experience data; and

            3. List of contractor’s equipment units, which are owned, leased, and/or under purchase agreements, supported by certification of availability of equipment from the equipment lessor/vendor for the duration of the project; and

          3. Sworn statement in accordance with Section 25.2(b)(iv) of the IRR of RA 9184 and using the form prescribed in Section IX. Bidding Forms

      1. Documents Comprising the Bid: Financial Component

      2. Unless otherwise stated in the BDS, the financial component of the bid shall contain the following:

        1. Financial Bid Form in accordance with the form prescribed in Section IX. Bidding Forms; and

        2. Any other document required in the BDS.

      3. Unless indicated in the BDS, all Bids that exceed the ABC shall not be accepted.

      4. Alternative Bids

      5. Alternative Bids shall be rejected. For this purpose, alternative bid is an offer made by a Bidder in addition or as a substitute to its original bid which may be included as part of its original bid or submitted separately therewith for purposes of bidding. A bid with options is considered an alternative bid regardless of whether said bid proposal is contained in a single envelope or submitted in two (2) or more separate bid envelopes.

      6. Bidders shall submit offers that comply with the requirements of the Bidding Documents, including the basic technical design as indicated in the drawings and specifications. Unless there is a value engineering clause in the BDS, alternative bids shall not be accepted.

      7. Each Bidder shall submit only one Bid, either individually or as a partner in a JV. A Bidder who submits or participates in more than one bid (other than as a subcontractor if a subcontractor is permitted to participate in more than one bid) will cause all the proposals with the Bidder’s participation to be disqualified. This shall be without prejudice to any applicable criminal, civil and administrative penalties that may be imposed upon the persons and entities concerned.

      8. Bid Prices

      9. The contract shall be for the whole Works, as described in ITB Clause A, based on the priced Bill of Quantities submitted by the Bidder.

      10. The Bidder shall fill in rates and prices for all items of the Works described in the Bill of Quantities. Bids not addressing or providing all of the required items in the Bidding Documents including, where applicable, bill of quantities, shall be considered non-responsive and, thus, automatically disqualified. In this regard, where a required item is provided, but no price is indicated, the same shall be considered as non-responsive, but specifying a "0" (zero) for the said item would mean that it is being offered for free to the Government.

      11. All duties, taxes, and other levies payable by the Contractor under the Contract, or for any other cause, prior to the deadline for submission of bids, shall be included in the rates, prices, and total bid price submitted by the Bidder.

      12. Unless otherwise provided in the BDS, all bid prices for the given scope of work in the contract as awarded shall be considered as fixed prices, and therefore not subject to price escalation during contract implementation, except under extraordinary circumstances as indicated in the BDS and specified in GCC and its corresponding SCC provision.

      13. Bid Currencies

      14. All bid prices shall be quoted in Philippine Pesos unless otherwise provided in the BDS. However, for purposes of bid evaluation, bids denominated in foreign currencies shall be converted to Philippine currency based on the exchange rate prevailing on the day of the Bid opening.

      15. If so allowed in accordance with ITB Clause C, the Procuring Entity for purposes of bid evaluation and comparing the bid prices will convert the amounts in various currencies in which the bid price is expressed to Philippine Pesos at the exchange rate as published in the BSP reference rate bulletin on the day of the bid opening.

      16. Unless otherwise specified in the BDS, payment of the contract price shall be made in Philippine Pesos.

      17. Bid Validity

      18. Bids shall remain valid for the period specified in the BDSwhich shall not exceed one hundred twenty (120) calendar days from the date of the opening of bids.

      19. In exceptional circumstances, prior to the expiration of the bid validity period, the Procuring Entity may request Bidders to extend the period of validity of their bids. The request and the responses shall be made in writing. The bid security described in ITB Clause C should also be extended corresponding to the extension of the bid validity period at the least. A Bidder may refuse the request without forfeiting its bid security, but his bid shall no longer be considered for further evaluation and award. A Bidder granting the request shall not be required or permitted to modify its bid.

      20. Bid Security

      21. The bid security in the amount stated in the BDS shall be equal to the percentage of the ABC in accordance with the following schedule:

              Form of Bid Security

              Amount of Bid Security

              (Equal to Percentage of the ABC)

              1. Cash or cashier’s/manager’s check issued by a Universal or Commercial Bank.

              Two percent (2%)

              1. Bank draft/guarantee or irrevocable letter of credit issued by a Universal or Commercial Bank: Provided, however, that it shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank.

              1. Surety bond callable upon demand issued by a surety or insurance company duly certified by the Insurance Commission as authorized to issue such security; and/or

              Five percent (5%)

              1. Any combination of the foregoing.

              Proportionate to share of form with respect to total amount of security

        For biddings conducted by local government units, the Bidder may also submit bid securities in the form of cashier’s/manager’s check, bank draft/guarantee, or irrevocable letter of credit from other banks certified by the BSP as authorized to issue such financial statement.

      22. The bid security should be valid for the period specified in the BDS. Any bid not accompanied by an acceptable bid security shall be rejected by the Procuring Entity as non-responsive.

      23. No bid securities shall be returned to bidders after the opening of bids and before contract signing, except to those that failed or declared as post-disqualified, upon submission of a written waiver of their right to file a motion for reconsideration and/or protest. Without prejudice on its forfeiture, Bid Securities shall be returned only after the bidder with the Lowest Calculated Responsive Bid has signed the contract and furnished the Performance Security, but in no case later than the expiration of the Bid Security validity period indicated in ITB Clause C.

      24. Upon signing and execution of the contract, pursuant to ITB Clause F, and the posting of the performance security, pursuant to ITB Clause F, the successful Bidder’s Bid security will be discharged, but in no case later than the Bid security validity period as indicated in ITB Clause C.

      25. The bid security may be forfeited:

        1. if a Bidder:

          1. withdraws its bid during the period of bid validity specified in ITB Clause 17;

          2. does not accept the correction of errors pursuant to ITB Clause E;

          3. fails to submit the requirements within the prescribed period, or a finding against their veracity, as stated in ITB Clause E; or

          4. any other reason stated in the BDS.

        2. if the successful Bidder:

          1. fails to sign the contract in accordance with ITB Clause F;

          2. fails to furnish performance security in accordance with ITB Clause F; or

          3. any other reason stated in the BDS.

      26. Format and Signing of Bids

      27. Bidders shall submit their bids through their duly authorized representative using the appropriate forms provided in Section IX. Bidding Forms on or before the deadline specified in the ITB Clause D in two (2) separate sealed bid envelopes, and which shall be submitted simultaneously. The first shall contain the technical component of the bid, including the eligibility requirements under ITB Clause C, and the second shall contain the financial component of the bid.

      28. Forms as mentioned in ITB Clause C must be completed without any alterations to their format, and no substitute form shall be accepted. All blank spaces shall be filled in with the information requested.

      29. The Bidder shall prepare an original of the first and second envelopes as described in ITB Clauses C and C. In addition, the Bidder shall submit copies of the first and second envelopes. In the event of any discrepancy between the original and the copies, the original shall prevail.

      30. The bid, except for unamended printed literature, shall be signed, and each and every page thereof shall be initialed, by the duly authorized representative/s of the Bidder.

      31. Any interlineations, erasures, or overwriting shall be valid only if they are signed or initialed by the duly authorized representative/s of the Bidder.

      32. Sealing and Marking of Bids

      33. Unless otherwise indicated in the BDS,Bidders shall enclose their original eligibility and technical documents described in ITB Clause C, in one sealed envelope marked “ORIGINAL - TECHNICAL COMPONENT”, and the original of their financial component in another sealed envelope marked “ORIGINAL - FINANCIAL COMPONENT”, sealing them all in an outer envelope marked “ORIGINAL BID”.

      34. Each copy of the first and second envelopes shall be similarly sealed duly marking the inner envelopes as “COPY NO. ___ - TECHNICAL COMPONENT” and “COPY NO. ___ – FINANCIAL COMPONENT” and the outer envelope as “COPY NO. ___”, respectively. These envelopes containing the original and the copies shall then be enclosed in one single envelope.

      35. The original and the number of copies of the Bid as indicated in the BDS shall be typed or written in indelible ink and shall be signed by the bidder or its duly authorized representative/s.

      36. All envelopes shall:

        1. contain the name of the contract to be bid in capital letters;

        2. bear the name and address of the Bidder in capital letters;

        3. be addressed to the Procuring Entity’s BAC identified in ITB Clause B;

        4. bear the specific identification of this bidding process indicated in the Invitation to Bid; and

        5. bear a warning “DO NOT OPEN BEFORE…” the date and time for the opening of bids, in accordance with ITB Clause D.

      37. If bids are not sealed and marked as required, the Procuring Entity will assume no responsibility for the misplacement or premature opening of the bid.

bmission and Opening of Bids

      1. Deadline for Submission of Bids

Bids must be received by the Procuring Entity’s BAC at the address and on or before the date and time indicated in the BDS.

      1. Late Bids

Any bid submitted after the deadline for submission and receipt of bids prescribed by the Procuring Entity, pursuant to ITB Clause D, shall be declared “Late” and shall not be accepted by the Procuring Entity.

      1. Modification and Withdrawal of Bids

      2. The Bidder may modify its bid after it has been submitted; provided that the modification is received by the Procuring Entity prior to the deadline prescribed for submission and receipt of bids. The Bidder shall not be allowed to retrieve its original bid, but shall be allowed to submit another bid equally sealed, properly identified, linked to its original bid marked as “TECHNICAL MODIFICATION” or “FINANCIAL MODIFICATION” and stamped “received” by the BAC. Bid modifications received after the applicable deadline shall not be considered and shall be returned to the Bidder unopened.

      3. A Bidder may, through a letter of withdrawal, withdraw its bid after it has been submitted, for valid and justifiable reason; provided that the letter of withdrawal is received by the Procuring Entity prior to the deadline prescribed for submission and receipt of bids.

      4. Bids requested to be withdrawn in accordance with ITB Clause D shall be returned unopened to the Bidders. A Bidder may also express its intention not to participate in the bidding through a letter which should reach and be stamped by the BAC before the deadline for submission and receipt of bids. A Bidder that withdraws its bid shall not be permitted to submit another bid, directly or indirectly, for the same contract.

      5. No bid may be modified after the deadline for submission of bids. No bid may be withdrawn in the interval between the deadline for submission of bids and the expiration of the period of bid validity specified by the Bidder on the Financial Bid Form. Withdrawal of a bid during this interval shall result in the forfeiture of the Bidder’s bid security, pursuant to ITB Clause C, and the imposition of administrative, civil, and criminal sanctions as prescribed by RA 9184 and its IRR.

      6. Opening and Preliminary Examination of Bids

      7. The BAC shall open the first bid envelopes of Bidders in public as specified in the BDS to determine each Bidder’s compliance with the documents prescribed in ITB Clause C. For this purpose, the BAC shall check the submitted documents of each bidder against a checklist of required documents to ascertain if they are all present, using a non-discretionary “pass/fail” criterion. If a bidder submits the required document, it shall be rated “passed” for that particular requirement. In this regard, bids that fail to include any requirement or are incomplete or patently insufficient shall be considered as “failed”. Otherwise, the BAC shall rate the said first bid envelope as “passed”.

      8. Immediately after determining compliance with the requirements in the first envelope, the BAC shall forthwith open the second bid envelope of each remaining eligible bidder whose first bid envelope was rated “passed”. The second envelope of each complying bidder shall be opened within the same day. In case one or more of the requirements in the second envelope of a particular bid is missing, incomplete or patently insufficient, and/or if the submitted total bid price exceeds the ABC unless otherwise provided in ITB Clause C, the BAC shall rate the bid concerned as “failed”. Only bids that are determined to contain all the bid requirements for both components shall be rated “passed” and shall immediately be considered for evaluation and comparison.

      9. Letters of withdrawal shall be read out and recorded during bid opening, and the envelope containing the corresponding withdrawn bid shall be returned to the Bidder unopened. If the withdrawing Bidder’s representative is in attendance, the original bid and all copies thereof shall be returned to the representative during the bid opening. If the representative is not in attendance, the Bid shall be returned unopened by registered mail. The Bidder may withdraw its bid prior to the deadline for the submission and receipt of bids, provided that the corresponding letter of withdrawal contains a valid authorization requesting for such withdrawal, subject to appropriate administrative sanctions.

      10. If a Bidder has previously secured a certification from the Procuring Entity to the effect that it has previously submitted the above-enumerated Class “A” Documents, the said certification may be submitted in lieu of the requirements enumerated in ITB Clause C, items (i) to (vi).

      11. In the case of an eligible foreign Bidder as described in ITB Clause A, the Class “A” Documents enumerated in ITB Clause C may be substituted with the appropriate equivalent documents, if any, issued by the country of the foreign Bidder concerned.

      12. Each partner of a joint venture agreement shall likewise submit the documents required in ITB Clauses C and C. Submission of documents required under ITB Clauses C to C by any of the joint venture partners constitutes compliance.

      13. A Bidder determined as “failed” has three (3) calendar days upon written notice or, if present at the time of bid opening, upon verbal notification within which to file a request for reconsideration with the BAC: Provided, however, that the request for reconsideration shall not be granted if it is established that the finding of failure is due to the fault of the Bidder concerned: Provided, further, that the BAC shall decide on the request for reconsideration within seven (7) calendar days from receipt thereof. If a failed Bidder signifies his intent to file a request for reconsideration, the BAC shall keep the bid envelopes of the said failed Bidder unopened and/or duly sealed until such time that the request for reconsideration or protest has been resolved.

E.Evaluation and Comparison of Bids

      1. Process to be Confidential

      2. Members of the BAC, including its staff and personnel, as well as its Secretariat and TWG, are prohibited from making or accepting any kind of communication with any bidder regarding the evaluation of their bids until the issuance of the Notice of Award, unless otherwise allowed in the BDS or in the case of ITB Clause 26.

      3. Any effort by a bidder to influence the Procuring Entity in the Procuring Entity’s decision in respect of Bid evaluation, Bid comparison or contract award will result in the rejection of the Bidder’s Bid.

      4. Clarification of Bids

To assist in the evaluation, comparison and post-qualification of the bids, the Procuring Entity may ask in writing any Bidder for a clarification of its bid. All responses to requests for clarification shall be in writing. Any clarification submitted by a Bidder in respect to its bid and that is not in response to a request by the Procuring Entity shall not be considered

      1. Detailed Evaluation and Comparison of Bids

      2. The Procuring Entity will undertake the detailed evaluation and comparison of Bids which have passed the opening and preliminary examination of Bids, pursuant to ITB Clause 24, in order to determine the Lowest Calculated Bid.

      3. In evaluating the Bids to get the Lowest Calculated Bid, the Procuring Entity shall undertake the following:

        1. The detailed evaluation of the financial component of the bids, to establish the correct calculated prices of the bids; and

        2. The ranking of the total bid prices as so calculated from the lowest to highest. The bid with the lowest price shall be identified as the Lowest Calculated Bid.

      4. The Procuring Entity's BAC shall immediately conduct a detailed evaluation of all bids rated “passed,” using non-discretionary “pass/fail” criterion. Unless otherwise specified in the BDS, the BAC shall consider the following in the evaluation of bids:

        1. Completeness of the bid. Unless the ITB specifically allows partial bids, bids not addressing or providing all of the required items in the Schedule of Requirements including, where applicable, bill of quantities, shall be considered non-responsive and, thus, automatically disqualified. In this regard, where a required item is provided, but no price is indicated, the same shall be considered as non-responsive, but specifying a "0" (zero) for the said item would mean that it is being offered for free to the Procuring Entity; and

        2. Arithmetical corrections. Consider computational errors, omissions, and other bid modifications, if allowed in the BDS, to enable proper comparison of all eligible bids. Any adjustment shall be calculated in monetary terms to determine the calculated prices.

      5. Based on the detailed evaluation of bids, those that comply with the above-mentioned requirements shall be ranked in the ascending order of their total calculated bid prices, as evaluated and corrected for computational errors, discounts and other modifications, to identify the Lowest Calculated Bid. Total calculated bid prices, as evaluated and corrected for computational errors, discounts and other modifications, which exceed the ABC shall not be considered.

      6. Unless otherwise indicated in the BDS, the Procuring Entity’s evaluation of bids shall only be based on the bid price quoted in the Financial Bid Form

      7. Bids shall be evaluated on an equal footing to ensure fair competition. For this purpose, all bidders shall be required to include in their bids the cost of all taxes, such as, but not limited to, value added tax (VAT), income tax, local taxes, and other fiscal levies and duties which shall be itemized in the bid form and reflected in the detailed estimates. Such bids, including said taxes, shall be the basis for bid evaluation and comparison.

      8. Post Qualification

      9. The Procuring Entity shall determine to its satisfaction whether the Bidder that is evaluated as having submitted the Lowest Calculated Bid (LCB) complies with and is responsive to all the requirements and conditions specified in ITB Clauses 5, C, and C.

      10. Within a non-extendible period of three (3) calendar days from receipt by the Bidder of the notice from the BAC that it submitted the LCB, the Bidder shall submit the following documentary requirements:

        1. Tax clearance per Executive Order 398, Series of 2005;

        2. Latest income and business tax returns in the form specified in the BDS;

        3. Certificate of PhilGEPS Registration; and

        4. Other appropriate licenses and permits required by law and stated in the BDS.

Failure of the Bidder declared as LCB to duly submit the requirements under thisClause or a finding against the veracity of such, shall be ground for forfeiture of the bid security and disqualification of the Bidder for award.

      1. The determination shall be based upon an examination of the documentary evidence of the Bidder’s qualifications submitted pursuant to ITB Clauses C and C, as well as other information as the Procuring Entity deems necessary and appropriate, using a non-discretionary “pass/fail” criterion.

      2. If the BAC determines that the Bidder with the Lowest Calculated Bid passes all the criteria for post-qualification, it shall declare the said bid as the Lowest Calculated Responsive Bid, and recommend to the Head of the Procuring Entity the award of contract to the said Bidder at its submitted price or its calculated bid price, whichever is lower, subject to ITB Clause F.

      3. A negative determination shall result in rejection of the Bidder’s Bid, in which event the Procuring Entity shall proceed to the next Lowest Calculated Bid to make a similar determination of that Bidder’s capabilities to perform satisfactorily. If the second Bidder, however, fails the post qualification, the procedure for post qualification shall be repeated for the Bidder with the next Lowest Calculated Bid, and so on until the Lowest Calculated and Responsive Bid is determined for contract award.

      4. Within a period not exceeding seven (7) calendar days from the date of receipt of the recommendation of the BAC, the Head of the Procuring Entity shall approve or disapprove the said recommendation. In the case of government owned and government-owned and/or -controlled corporations (GOCCs) and government financial institutions (GFIs), the period provided herein shall be fifteen (15) calendar days.

      5. Reservation Clause

      6. Notwithstanding the eligibility or post-qualification of a bidder, the Procuring Entity concerned reserves the right to review its qualifications at any stage of the procurement process if it has reasonable grounds to believe that a misrepresentation has been made by the said bidder, or that there has been a change in the Bidder’s capability to undertake the project from the time it submitted its eligibility requirements. Should such review uncover any misrepresentation made in the eligibility and bidding requirements, statements or documents, or any changes in the situation of the Bidder which will affect its capability to undertake the project so that it fails the preset eligibility or bid evaluation criteria, the Procuring Entity shall consider the said Bidder as ineligible and shall disqualify it from submitting a bid or from obtaining an award or contract.

      7. Based on the following grounds, the Procuring Entity reserves the right to reject any and all Bids, declare a Failure of Bidding at any time prior to the contract award, or not to award the contract, without thereby incurring any liability, and make no assurance that a contract shall be entered into as a result of the bidding:

        1. if there is prima facie evidence of collusion between appropriate public officers or employees of the Procuring Entity, or between the BAC and any of the bidders, or if the collusion is between or among the bidders themselves, or between a bidder and a third party, including any act which restricts, suppresses or nullifies or tends to restrict, suppress or nullify competition;

        2. if the Procuring Entity’s BAC is found to have failed in following the prescribed bidding procedures; or

        3. for any justifiable and reasonable ground where the award of the contract will not redound to the benefit of the Government as follows:

          1. If the physical and economic conditions have significantly changed so as to render the project no longer economically, financially or technically feasible as determined by the head of the procuring entity;

          2. If the project is no longer necessary as determined by the head of the procuring entity; and

          3. If the source of funds for the project has been withheld or reduced through no fault of the Procuring Entity.

      8. In addition, the Procuring Entity may likewise declare a failure of bidding when:

        1. No bids are received;

        2. All prospective bidders are declared ineligible;

        3. All bids fail to comply with all the bid requirements or fail post-qualification; or

        4. The bidder with the Lowest Calculated Responsive Bid refuses, without justifiable cause to accept the award of contract, and no award is made.

F.Award of Contract

      1. Contract Award

      2. Subject to ITB Clause E, the Procuring Entity shall award the contract to the Bidder whose Bid has been determined to be the Lowest Calculated and Responsive Bid (LCRB).

      3. Prior to the expiration of the period of Bid validity, the Procuring Entity shall notify the successful Bidder in writing that its Bid has been accepted, through a Notice of Award received personally or sent by registered mail or electronically, receipt of which must be confirmed in writing within two (2) days by the LCRB and submitted personally or sent by registered mail or electronically to the Procuring Entity.

      4. Notwithstanding the issuance of the Notice of Award, award of contract shall be subject to the following conditions:

        1. Submission of the following documents within the prescribed period from receipt by the Bidder of the notice that it has the Lowest Calculated and Responsive Bid:

          1. Valid JVA, if applicable, within ten (10) calendar days;

          2. Valid PCAB license and registration for the type and cost of the contract to be bid for foreign bidders, within thirty (30) calendar days, if allowed under a Treaty or International or Executive Agreement mentioned in ITB Clause C;

        2. Posting of the performance security in accordance with ITB Clause F;

        3. Signing of the contract as provided in ITB Clause F; and

        4. Approval by higher authority, if required.

      5. Signing of the Contract

      6. At the same time as the Procuring Entity notifies the successful Bidder that its Bid has been accepted, the Procuring Entity shall send the Contract Form to the Bidder, which Contract has been provided in the Bidding Documents, incorporating therein all agreements between the parties.

      7. Within ten (10) calendar days from receipt of the Notice of Award, the successful Bidder shall post the required performance security, sign and date the contract and return it to the Procuring Entity.

      8. The Procuring Entity shall enter into contract with the successful Bidder within the same ten (10) calendar day period provided that all the documentary requirements are complied with.

      9. The following documents shall form part of the contract:

        1. Contract Agreement;

        2. Bidding Documents;

        3. Winning bidder’s bid, including the Technical and Financial Proposals, and all other documents/statements submitted;

        4. Performance Security;

        5. Credit line in accordance with ITB Clause A, if applicable;

        6. Notice of Award of Contract; and

        7. Other contract documents that may be required by existing laws and/or specified in the BDS.

      10. Performance Security

      11. To guarantee the faithful performance by the winning Bidder of its obligations under the contract, it shall post a performance security within a maximum period of ten (10) calendar days from the receipt of the Notice of Award from the Procuring Entity and in no case later than the signing of the contract.

      12. The performance security shall be denominated in Philippine Pesos and posted in favor of the Procuring Entity in an amount equal to the percentage of the total contract price in accordance with the following schedule:

              Form of Performance Security

              Amount of Performance Security

              (Equal to Percentage of the Total Contract Price)

              1. Cash or cashier’s/manager’s check issued by a Universal or Commercial Bank.

              Ten percent (10%)

              1. Bank draft/guarantee or irrevocable letter of credit issued by a Universal or Commercial Bank: Provided, however, that it shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank.

              1. Surety bond callable upon demand issued by a surety or insurance company duly certified by the Insurance Commission as authorized to issue such security; and/or

              Thirty percent (30%)

              1. Any combination of the foregoing.

              Proportionate to share of form with respect to total amount of security

      13. Failure of the successful Bidder to comply with the above-mentioned requirement shall constitute sufficient ground for the annulment of the award and forfeiture of the bid security, in which event the Procuring Entity shall initiate and complete the post qualification of the second Lowest Calculated Bid. The procedure shall be repeated until the Lowest Calculated and Responsive Bid is identified and selected for contract award. However if no Bidder passed post-qualification, the BAC shall declare the bidding a failure and conduct a re-bidding with re-advertisement.

      14. Notice to Proceed

      15. Within three (3) calendar days from the date of approval of the Contract by the appropriate government approving authority, the Procuring Entity shall issue its Notice to Proceed to the Bidder.

      16. The date of the Bidder’s receipt of the Notice to Proceed will be regarded as the effective date of the Contract, unless otherwise specified in the BDS.











Section III.

Bid Data Sheet

Bid Data Sheet

ITB CLAUSE

1.1

The PROCURING ENTITY is PHILIPPINE PORTS AUTHORITY-PMO SOUTH HARBOR

The name of the Contract is REPAIR OF ROCK BULKHEAD & REPAIR/REPAINTING OF FERRY LANDING TERMINAL AT SLIP 14, SOUTH HARBOR, PORT AREA, MANILA.

2

The Funding Source is:

The Philippine Ports Authority through the Corporate Budget of the Authority for CY 2012 in the amount of P 3,277,520.00.

The name of the Project is Repair of rock bulkhead & repair/repainting of ferry landing terminal at Slip 14, South Harbor, Port Area, Manila. (PMOSH-RM0512-A120056)

5.1

No further instructions.

5.2

No Treaty or International or Executive Agreement allows participation of foreign bidders. Bidding is restricted to eligible bidders

5.4

The Bidder must have completed, within the period specified in the Invitation to Bid and ITB Clause 12.1(a)(iii), a single contract that is similar to this Project, equivalent to at least fifty percent (50%) of the ABC.

For this purpose, similar contracts shall refer to those which are similar in nature and complexity of the contract to be bid as described / enumerated in the scope of works

5.5

No further instructions.

6.3

Qualified Technical Personnel should undertake the inspection.

7

No further instructions.

8

"Not applicable"

9.1

The Procuring Entity will hold a Pre-Bid Conference for this Project on:

August 09, 2011 ; 10:00 A.M.

ESD Conference Room, Mezanine, ESD PMO South Harbor PDO- Mla –NL Bldg.

South Harbor, Port Area, Manila

10.01

The Procuring Entity's address is:

PPA- PMO South Harbor, PDO-Mla. Bldg., South Harbor, Port Area, Manila

ENGR. ANDRES C. CANDAROMA, JR.

ESD Manager / Chairman BAC – Engineering Projects

Telephone No.: (02) 527-6671 / (02) 525-5264 loc. 522 / 523 / 524

E-Mail Address:

I2.1(a)(i)

No additional Requirements

12.1(a)(iii)

No further instructions.

12.1(a)(iv)

No further instructions.

13.1

Detailed estimates including summary sheet indicating the unit prices of construction materials, labor rates and equipment rentals used in the coming up with the bid. Also Cash Flow by Quarter & Payment Schedule.

13.2

The ABC is P 3,277,520.00. Any bid with a financial component exceeding this amount shall not be accepted'.

15.4

Bid Prices shall be fixed. Adjustable price proposals shall be treated as non-responsive and shall be rejected.

Price escalation may be allowed in extraordinary circumstances as may be determined by the National Economic and Development Authority in accordance with the Civil Code of the Philippines, and upon the recommendation of the Procuring Entity.

16.1

The bid prices shall be quoted in Philippine Pesos.

17.1

Bids will be valid until (not exceeding One Hundred Twenty (120) days from the date of the opening of bids.

18.1

The bid security shall be in the following amount:

I. P 65,550.40if bid security is in cash, cashier's/manager's check, bank draft/guarantee or irrevocable letter of credit;

  1. P 163,876.00 if bid security is in Surety Bond; (it must be Surety Bond in the form of Bidders Bond) or

  1. Any combination of the foregoing proportionate to the share of form with respect to total amount of security.

18.2;18.3; and 18.4

The bid security shall be valid until (One Hundred Twenty (120) days from the date set for Bid Opening.

18.5(a)(iv)

  1. Submission of eligibility requirements containing false information or falsified documents.

  2. Submission of bids that contain false information or falsified documents, or the concealment of such information in the bids in order to influence the outcome of eligibility screening or any other stage of the public bidding.

3. Allowing the use of one's name, or using the name of another for purpose of public bidding.

  1. Withdrawal of a bid, or refusal to accept an award, or enter into contract with the Government without justifiable cause, after the Bidder had been adjudged as having submitted the Lowest Calculated and Responsive Bid.

  2. Refusal or failure to post the required performance security within the
    within the prescribed time.

  1. Refusal to clarify or validate in writing its bid during post-qualification within
    a period of seven (7) calendar days from receipt of the request for clarification.

  2. Any documented unsolicited attempt by a bidder to unduly influence the
    outcome of the bidding in his favor.

8. Failure of the potential joint venture partners to enter into the joint venture after the bid is declared successful.

9. All other acts that tend to defeat the purpose of competitive bidding, such as habitually withdrawing from bidding, submitting late bids or patently insufficient bid, for at least three (3) times within a year, except for valid reasons

20.

20.3

Failure to comply with the required Sealing and Marking of bids

shall be a ground for disqualification.

Each Bidder shall submit ONE (1) ORIGINAL and THREE (3)sets of certified true copies reproduced from the original and must be authenticated.

All pages of the Eligibility requirements, Bid Security, Project Requirements and Omnibus Sworn Statements should be signed or authenticated by the authorized signing official designated for the project applied for. Failure to comply with this requirement shall be a ground for ineligibility. By signing or authenticating each page of the Eligibility requirements, Bid Security, Project requirements and Omnibus Sworn Statements, the Contractor or his duly authorized representative acknowledges the truth and correctness of all statements made therein, as well as the authenticity of the documents supporting it. Submission of false statements and/or misrepresentation and/or withholding of required pertinent information shall be a ground for disqualification and imposition of the applicable sanctions in the IRR of R.A. 9184.

For easy reference all pages shall be numbered consecutively and with the corresponding index tab. Failure to comply will be a ground for disqualification.

21

The address for submission of bids is.

BAC Office, Engineering Services Division

PPA-PMO South Harbor, Mezanine, PDO-Mla Bldg.,

MDSF St., South Harbor, Port Area, Manila

The deadline for submission of bids is.

August 23, 2011 ; 9:00 A.M.

24.1

The place of bid opening is:

ESD Conference Room, PDO-Mla. Bldg., MDSF St., South Harbor, Port Area, Manila

The date and time of bid opening

August 23, 2011, 10:00 A.M.

27.3(b)

Arithmetical Correction is allowed

28.2(b)

The latest income tax and business tax returns are those within the last six (6) months preceding the date of bid submission

28.2.(d)

None

3 I .4(g)

Construction Schedule and S-curve with PERT-CPM, Manpower Schedule, Construction Methods, Equipment Utilization schedule, Construction Safety and Health Program submitted for approval and duly received by the Department of Labor and Employment, Certificate and Affidavit of Site Inspection and VAT Certificate Registration.

33.2

The effective date of the Contract is not later than Seven (7) Calendar days from the issuance of the Notice to Proceed









37



Скачать документ

Похожие документы:

  1. Annual ti added 2006 cyf – 3402 hcpl (18 943) bib# call processed 854507 null air space

    Документ
    ... and federal district courts 335003 ... manual 808076 3658401 Goe Quality management ... Mockingbird a portrait of Harper Lee 790117 B Lee ... Noelle the bulldog 760595 Est ... H Hum saathsaath hain Hama sathasatha haim 798694 ... a Prada bag to the unemployment office a ...
  2. Contents (active hyperlinks CTRL + click to follow link)

    Документ
    ... by Theodor Adorno (Harper, New York, ... president José Manuel Barroso earlier expressed ... ." The Home Officesaid: "This is ... as the district's mayor stood helplessly ... examples: Finland, Baltic states. b. An ... part of “acquisition management”. 3.29 How to stay ...
  3. Twentieth century legal treatises fiche listing

    Документ
    ... by Harriet Stanton Blatch. Fiche: 1,998 ... b. 1855. A manual of corporate management : containing forms, ... government. New York : Harper & Bros. 1916 ... 1920, part IV and part V). London : Sweet and ... crime from the district attorney's office. New York ...
  4. Mailorderlist 16 09 2012 sort by label your filter settings for this list

    Документ
    ... , were two abandoned office buildings. both have been ... part of each side. Tracklist: A. Runzelstirn und Gurgelstock - Mahnmal ... Katsura district, he never quite managed to ... outside Stø (2006) Harbour seals (Phoca vitulina) ... . This new blitz 7″ sounds ...
  5. CHART OF ACCOUNTS KNOXVILLE REQ NO

    Документ
    ... OF SOUTH CAROLINA-PINKLE B01998422 PROCUREMENT OFFICE E01-0170 BUSINESS SERVICES RECORDS MANAGEMENT ... BLDG EQUIP E01-0145-07 SCIENTIFIC EQUIPMENT PURCHASES E01-0145-08 PORT ...

Другие похожие документы..